Release Calendar - April 2008

Other release listings for viewing:

April 2008

Sunday
Monday
Tuesday
Wednesday
Thursday
Friday
Saturday
Week 14
1
2
3
4
5
   

ICE
WCR

Project Office
Migration of Faculty of Law staff to Lotus Notes
   

Data network
VERN

NIS
Commission of Peninsula/ Caulfield network infrastructure
 

Server Hosting
Netware Data Migration

EWS
Migration of AAF dept / Fac of Business & Economics data to new data servers
Week 15
6
7
8
9
10
11
12
 
Project Office
Availability of PDA EasySync product for Lotus Note

Business Intelligence
SAP Income release 1B pt1

Application Admin
Part release - package to be reassessed for re-release
 

Data network
VERN

NIS
Chg TBA
Commission of Clayton / Moe high speed network link. Delayed date TBA
NIS
Enable ports on network for VoIP at building 28

Data network
VERN

NIS
Chg TBA
Commission of Churchill / Moe high speed network link. Delayed date TBA
Week 16
13
14
15
16
17
18
19
 

 

 

ICE
WCR

Project Office
Migration of Audit & Risk Management staff to Lotus Notes

Data network
VERN

NIS
Chg TBA
Commission of Latrobe Hospital to Churchill & Clayton - 2 high speed network links. Delayed date TBA
Project Office
Configuration Mgmt database Go Live
 
NIS
Enable ports on networks for VoIP for all Clayton buildings

ICE
WCR

Project Office
Faculty of Education migration to Lotus Notes (Pilot for business)
NIS
Migrate the rest of Monash staff workstations/laptops to the new Monash Internet Service
Week 17
20
21
22
23
24
25
26
 

ICE
WCR

Project Office
HR Migration to Lotus Notes (Pilot for business)
 
NIS
Go Live only. Does not include Berwick migration.

Data network
VERN

NIS
Chg TBA
Commission of Warrigal Hospital to Clayton high speed network links. Delayed date TBA

Data network
VERN

NIS
Chg TBA
Commission of Warrigal Hospital to Churchill high speed network links. Delayed date TBA
 
NIS
Enable ports on networks for VoIP for all Caulfield, Parkville, 30CSM, 472BSM, Peninsula, Berwick & Gippsland
NIS
Redirect all Monash staff NOT using new Monash Internet Service to migration instructions on how to do so.

Data network
VERN

NIS
Connection of Parkville VCP <-> Clayton ; Peninsula <-> Clayton & Gippsland <-> Berwick high speed network links.

my.Monash Portal
Worklog

FLT
Commission of Worklog system for project staff. Go Live date

Data network
VERN

NIS
Commission of Parkville VCP to Clayton high speed network links.
Week 18
27
28
29
30
     
 
Application Admin
Online application, selection mgmt, offer letters and payment for use by IRS. Rescheduled from 21st April.
         